West End Sunnyside
Sunnyside (Trinity Bay), Newfoundland and Labrador
Federal contribution
$189,349
Federal share33%
of $573.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.5 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Sunnyside
- Construction start
- Sep 29, 2010(actual)
- Construction end
- Mar 31, 2013(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2010
- Construction end2.3 years lateforecast Nov 30, 2010
Also in Sunnyside (Trinity Bay)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18763 in the federal list. How to read these figures.