Centre Hill Wilderness Trail Repairs and Enhancement
Sunnyside (Trinity Bay), Newfoundland and Labrador
Federal contribution
$15,000
Federal share50%
of $30.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Town of Sunnyside
- Construction start
- Apr 15, 2015(actual)
- Construction end
- Dec 17, 2015(actual)
Also in Sunnyside (Trinity Bay)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50649 in the federal list. How to read these figures.