Back to projects

Centre Hill Wilderness Trail Repairs and Enhancement

Sunnyside (Trinity Bay), Newfoundland and Labrador

completeRecreationNRT
Federal contribution
$15,000
Federal share50%

of $30.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 13 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Town of Sunnyside
Construction start
Apr 15, 2015(actual)
Construction end
Dec 17, 2015(actual)

Also in Sunnyside (Trinity Bay)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50649 in the federal list. How to read these figures.