Back to projects

Water Supply Improvement

Steady Brook, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$82,806
Federal share33%

of $248.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.4 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Steady Brook
Construction start
Nov 4, 2010(actual)
Construction end
Nov 30, 2011(actual)

Against the original forecast

  • Construction start19 months lateforecast Apr 1, 2009
  • Construction end24 months lateforecast Dec 1, 2009