Water Supply Improvement
Steady Brook, Newfoundland and Labrador
Federal contribution
$82,806
Federal share33%
of $248.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.4 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Steady Brook
- Construction start
- Nov 4, 2010(actual)
- Construction end
- Nov 30, 2011(actual)
Against the original forecast
- Construction start19 months lateforecast Apr 1, 2009
- Construction end24 months lateforecast Dec 1, 2009
Also in Steady Brook