Victoria Park Tennis Court Development

Charlottetown, Prince Edward Island

completeSportMRIF
Federal contribution
$76,333
Federal share33%

of $229.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 5, 2008
20092010
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Apr 1, 2008(actual)
Construction end
Dec 30, 2009(actual)

Against the original forecast

  • Construction start4 months lateforecast Nov 28, 2007
  • Construction end19 months lateforecast Jun 6, 2008

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19388 in the federal list. How to read these figures.