Brighton & Beach Grove Lift Station Upgrading
Charlottetown, Prince Edward Island
Federal contribution
$49,057
Federal share31%
of $158.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 14, 2008
2008200920102011
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Jul 16, 2009(actual)
- Construction end
- Dec 30, 2010(actual)
Against the original forecast
- Construction start15 months lateforecast Apr 1, 2008
- Construction end2.2 years lateforecast Oct 31, 2008