Provincial Sludge Management Odour Control

Charlottetown, Prince Edward Island

completeWastewaterMRIF
Federal contribution
$166,666
Federal share33%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 14, 2008
20092010
Built

Approved 5 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Aug 18, 2008(actual)
Construction end
Mar 31, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2008
  • Construction end17 months lateforecast Oct 31, 2008