Calgary Public Building Renovations

Calgary, Alberta

completeGreen EnergyMRIF
Federal contribution
$1.9M
$1,904,600
Federal share12%

of $15.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2008
20092010
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Calgary
Construction start
Mar 17, 2008(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Mar 1, 2008
  • Construction end5 months lateforecast Mar 31, 2010

Also in Calgary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19494 in the federal list. How to read these figures.