Upgrading of the Little Current Wastewater System
Federal contribution
$401,000
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 4, 2008
2009
Built
Approved 7 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Northeastern Manitoulin & The Islands
- Construction start
- Jun 11, 2008(actual)
- Construction end
- Aug 13, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 28, 2008
- Construction end20 months earlyforecast Mar 31, 2011