Upgrading of the Little Current Wastewater System

Little Current, Ontario

completeWastewaterMRIF
Federal contribution
$401,000
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 4, 2008
2009
Built

Approved 7 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 11, 2008(actual)
Construction end
Aug 13, 2009(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 28, 2008
  • Construction end20 months earlyforecast Mar 31, 2011

Also in Little Current

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19613 in the federal list. How to read these figures.