Recreation Centre Energy Improvements

Little Current, Ontario

completeGreen EnergyCC Top Up
Federal contribution
$136,967
Federal share33%

of $410.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Dec 9, 2009(actual)
Construction end
Mar 20, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Aug 1, 2009
  • Construction end5 weeks lateforecast Feb 15, 2011

Also in Little Current

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27150 in the federal list. How to read these figures.