Combined sewer separation

Brockville, Ontario

completeWastewaterMRIF
Federal contribution
$798,053
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2008
2009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Brockville
Construction start
May 28, 2008(actual)
Construction end
Nov 9, 2009(actual)

Against the original forecast

  • Construction end17 months earlyforecast Mar 31, 2011