Winsloe Soccer Club
Charlottetown, Prince Edward Island
Federal contribution
$60,000
Federal share33%
of $180.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 2, 2008
2009
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Oct 1, 2008(actual)
- Construction end
- Apr 30, 2009(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2008
- Construction end9 months lateforecast Jul 31, 2008
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19816 in the federal list. How to read these figures.