Parkman Soccer Complex Completion
Charlottetown, Prince Edward Island
Federal contribution
$61,666
Federal share33%
of $185.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 2, 2008
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Aug 13, 2008(actual)
- Construction end
- Oct 17, 2008(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Nov 15, 2008
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19821 in the federal list. How to read these figures.