The Charlottetown Civic Centre Roof Replacement

Charlottetown, Prince Edward Island

completeRecreationMRIF
Federal contribution
$111,125
Federal share28%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Aug 6, 2008(actual)
Construction end
Nov 28, 2008(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2008
  • Construction end5 months lateforecast Jun 30, 2008