Back to projects

Central Field Twinning

Charlottetown, Prince Edward Island

completeSportMRIF
Federal contribution
$72,706
Federal share33%

of $218.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 2, 2008
2009
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Jun 11, 2008(actual)
Construction end
Mar 31, 2009(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2008
  • Construction end6 months lateforecast Sep 30, 2008

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 20026 in the federal list. How to read these figures.