Central Field Twinning
Charlottetown, Prince Edward Island
Federal contribution
$72,706
Federal share33%
of $218.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 2, 2008
2009
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Jun 11, 2008(actual)
- Construction end
- Mar 31, 2009(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2008
- Construction end6 months lateforecast Sep 30, 2008
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 20026 in the federal list. How to read these figures.