TCH - Central Municipal Water & Sewer Infilling

Charlottetown, Prince Edward Island

completeWastewaterMRIF
Federal contribution
$339,817
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2008
2009201020112012
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Charlottetown
Construction start
Jul 16, 2008(actual)
Construction end
Nov 30, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast May 5, 2008
  • Construction end3.2 years lateforecast Sep 30, 2008