Back to projects

Road Reconstruction

Witless Bay, Newfoundland and Labrador

completeHighways and RoadsMRIF
Federal contribution
$112,719
Federal share29%

of $382.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Witless Bay
Construction start
Jun 2, 2009(actual)
Construction end
Oct 31, 2009(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 1, 2009

Also in Witless Bay