Harbour Road Shoreline Protection
Witless Bay, Newfoundland and Labrador
Federal contribution
$135,005
Federal share40%
of $337.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 18, 2021
20212022
Built
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Witless Bay
- Construction start
- Apr 11, 2022(actual)
- Construction end
- May 31, 2022(actual)
Against the original forecast
- Construction start8 weeks lateforecast Feb 15, 2022
- Construction end4 weeks earlyforecast Jun 30, 2022
Also in Witless Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56866 in the federal list. How to read these figures.