Harbour Road Shoreline Protection

Witless Bay, Newfoundland and Labrador

completeDisaster MitigationGIS
Federal contribution
$135,005
Federal share40%

of $337.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2021
20212022
Built

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Witless Bay
Construction start
Apr 11, 2022(actual)
Construction end
May 31, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Feb 15, 2022
  • Construction end4 weeks earlyforecast Jun 30, 2022

Also in Witless Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56866 in the federal list. How to read these figures.