Replacement of water and wastewater pipe networks

Saint-Quentin, New Brunswick

completeDrinking WaterCC
Federal contribution
$225,120
Federal share33%

of $675.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2009
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Saint-Quentin
Construction start
Jul 20, 2009(actual)
Construction end
Oct 9, 2009(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2009
  • Construction end2 months lateforecast Jul 31, 2009