Infrastructure Improvement Mgr Martin Street West

Saint-Quentin, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$451,813
Federal share43%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2018
20192020
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Saint-Quentin
Construction start
May 28, 2018(actual)
Construction end
Mar 20, 2020(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 1, 2018
  • Construction end4 months lateforecast Nov 30, 2019