Vanderhoof - 4th Street Improvement Program
Federal contribution
$1.8M
$1,759,933
Federal share33%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- District of Vanderhoof
- Construction start
- May 10, 2010(actual)
- Construction end
- Jun 9, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 15, 2010
- Construction end4 months earlyforecast Oct 1, 2011