Highway 16 - Holy Cross Hill Climbing Lane
Federal contribution
$957,750
Federal share50%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 19, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- May 17, 2010(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction end7 weeks lateforecast Sep 15, 2010
Also in Vanderhoof