completeWastewaterCC
Federal contribution
$100,050
Federal share33%

of $300.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Carrot River
Construction start
Jun 23, 2009(actual)
Construction end
Oct 1, 2009(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2009
  • Construction end2.5 years earlyforecast Mar 31, 2012