Carrot River Pedestrian Outback Trail Network
Federal contribution
$8,500
Federal share50%
of $17.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Town of Carrot River
- Construction start
- Apr 25, 2015(actual)
- Construction end
- Dec 18, 2015(actual)