Kamloops - Wastewater Treatment Plant Upgrade
Federal contribution
$7.1M
$7,100,000
Federal share33%
of $21.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 18, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Kamloops
- Construction start
- Nov 30, 2010(actual)
- Construction end
- Mar 31, 2015(actual)
Also in Kamloops
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22133 in the federal list. How to read these figures.