Kamloops Transit Maintenance Facility

Kamloops, British Columbia

completePublic TransitMIC
Federal contribution
$4.7M
$4,653,218
Federal share31%

of $14.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2010
2010201220142016
Built

Approved 8 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
May 2, 2011(actual)
Construction end
Dec 21, 2015(actual)

Against the original forecast

  • Construction end15 months earlyforecast Mar 31, 2017