Waterfront Development Site Services
Charlottetown, Prince Edward Island
Federal contribution
$349,879
Federal share30%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 5, 2008
200920102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Charlottetown
- Construction start
- Aug 3, 2009(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction end15 months lateforecast Oct 15, 2009