Tyne Valley Lagoon Expansion
Tyne Valley, Prince Edward Island
Federal contribution
$421,718
Federal share30%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2008
20092010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Community of Tyne Valley
- Construction start
- Jun 8, 2009(actual)
- Construction end
- Mar 1, 2010(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 30, 2008
- Construction end4 months lateforecast Nov 13, 2009