Tyne Valley Lagoon Expansion

Tyne Valley, Prince Edward Island

completeWastewaterCC
Federal contribution
$421,718
Federal share30%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2008
20092010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Community of Tyne Valley
Construction start
Jun 8, 2009(actual)
Construction end
Mar 1, 2010(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 30, 2008
  • Construction end4 months lateforecast Nov 13, 2009

Also in Tyne Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22177 in the federal list. How to read these figures.