Tyne Valley Events Center Rebuild

Tyne Valley, Prince Edward Island

completeRecreationGIS
Federal contribution
$4.0M
$3,999,791
Federal share40%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 13, 2020
20212022
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 17, 2020(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Nov 30, 2021