Main Street Upgrades
Federal contribution
$254,267
Federal share27%
of $930.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Souris
- Construction start
- Jun 7, 2010(actual)
- Construction end
- Sep 30, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 15, 2010
- Construction end2 months earlyforecast Nov 30, 2010
Also in Souris
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22250 in the federal list. How to read these figures.