Knights Avenue and Green Street Water & Sewer Upgrades

Souris, Prince Edward Island

completeWastewaterSCF
Federal contribution
$146,766
Federal share33%

of $440.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 4, 2016
20162017
Built

Approved 11 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Souris
Construction start
May 23, 2017(actual)
Construction end
Jun 26, 2017(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 1, 2016
  • Construction end12 months earlyforecast Jun 30, 2018