Grafton Street Pedestrian Pedway

Charlottetown, Prince Edward Island

completeCultureCC
Federal contribution
$525,000
Federal share25%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2009
200920102011
Built

Approved 6 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Mar 1, 2009(actual)
Construction end
Jan 24, 2011(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Apr 1, 2009
  • Construction end8 months lateforecast May 15, 2010

Also in Charlottetown