Georgetown Road Sewer Main Extension
Stratford, Prince Edward Island
Federal contribution
$153,797
Federal share25%
of $605.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2009
Built
Approved 6 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Stratford
- Construction start
- Jun 19, 2009(actual)
- Construction end
- Oct 14, 2009(actual)