Faulder Water System Improvements

Penticton, British Columbia

completeDrinking WaterCC
Federal contribution
$299,249
Federal share33%

of $915.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Construction start
Aug 1, 2013(actual)
Construction end
Mar 31, 2016(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2013

Also in Penticton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22282 in the federal list. How to read these figures.