Naramata Water System Upgrade
Federal contribution
$2.2M
$2,217,351
Federal share50%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Okanagan-Similkameen
- Construction start
- Jun 5, 2017(actual)
- Construction end
- Jun 15, 2018(actual)
Against the original forecast
- Construction end6 weeks lateforecast May 4, 2018
Also in Penticton
- Penticton Community Centre Expansion and Upgrade$7.7M
- Penticton - Ellis #4 Dam Upgrade$3.9M
- Okanagan Falls - Sewage Treatment Plant$3.1M
- Penticton - Penticton Creek Flood Mitigation: Reach 3AU/ 3B and Structure 3 and 4$3.0M
- Penticton - West Bench Improvement District Treated Water Supply and Upgrade$1.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49876 in the federal list. How to read these figures.