Penticton - West Bench Improvement District Treated Water Supply and Upgrade

Penticton, British Columbia

completeDrinking WaterCC
Federal contribution
$1.7M
$1,690,000
Federal share33%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2009
2009201120132015
Built

Approved 3 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Jul 30, 2012(actual)
Construction end
Mar 31, 2016(actual)

Against the original forecast

  • Construction start5 months earlyforecast Jan 1, 2013