Schedule
Announced and approvedMar 13, 2009
2010
Built
Approved 6 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Stratford
- Construction start
- Nov 2, 2009(actual)
- Construction end
- Aug 8, 2010(actual)
Against the original forecast
- Construction end2 months earlyforecast Oct 15, 2010