Allen / Mt Edward Rd Intersection Reconstruction
Charlottetown, Prince Edward Island
Federal contribution
$773,502
Federal share26%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2009
2010
Built
Approved 6 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Charlottetown
- Construction start
- Sep 28, 2009(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction end7 weeks lateforecast Oct 15, 2010
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22308 in the federal list. How to read these figures.