Canada Games Track & Field Complex

Charlottetown, Prince Edward Island

completeSportCC
Federal contribution
$236,269
Federal share32%

of $750.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2009
Built

Approved 6 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Jun 3, 2009(actual)
Construction end
Aug 14, 2009(actual)