Back to projects

Water Treatment Plant Disposal Sewer

Truro, Nova Scotia

completeWastewaterCC
Federal contribution
$88,842
Federal share33%

of $266.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2008
20092010
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Truro
Construction start
Oct 13, 2009(actual)
Construction end
Mar 23, 2010(actual)

Against the original forecast

  • Construction start13 months lateforecast Sep 1, 2008
  • Construction end12 months earlyforecast Mar 31, 2011

Also in Truro

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22355 in the federal list. How to read these figures.