Havre Boucher Waterwater Treatment and Collection System Upgrade
Federal contribution
$1.3M
$1,342,681
Federal share33%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 27, 2008
200920102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of County Of Antigonish
- Construction start
- Apr 13, 2010(actual)
- Construction end
- Oct 27, 2011(actual)
Against the original forecast
- Construction start2.1 years lateforecast Mar 20, 2008
- Construction end4 months lateforecast Jun 30, 2011
Also in Antigonish
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22357 in the federal list. How to read these figures.