Modelling structural changes in water and sewer mains
Federal contribution
$50,000
Federal share33%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.3 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Nov 20, 2008(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22389 in the federal list. How to read these figures.