Residential Water Metering Program

Antigonish, Nova Scotia

completeDrinking WaterCC
Federal contribution
$153,000
Federal share33%

of $459.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 27, 2008
2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Antigonish
Construction start
Apr 13, 2009(actual)
Construction end
Sep 16, 2009(actual)

Against the original forecast

  • Construction start11 months lateforecast May 1, 2008
  • Construction end18 months earlyforecast Mar 31, 2011

Also in Antigonish

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22416 in the federal list. How to read these figures.