Back to projects

New Water Treatment Plant

Cupar, Saskatchewan

completeDrinking WaterCC
Federal contribution
$1.7M
$1,714,000
Federal share33%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Cupar
Construction start
Sep 13, 2010(actual)
Construction end
Jul 31, 2012(actual)

Against the original forecast

  • Construction start16 months lateforecast May 1, 2009
  • Construction end2 months earlyforecast Sep 30, 2012

Also in Cupar

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22446 in the federal list. How to read these figures.