Back to projects

Muscowpetung Hill Reconstruction

Cupar, Saskatchewan

completeHighways and RoadsSCF
Federal contribution
$256,508
Federal share29%

of $886.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
20192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 15, 2020(actual)
Construction end
Jul 31, 2020(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Jun 30, 2020
  • Construction end4 weeks earlyforecast Aug 28, 2020

Also in Cupar