Lagoon Expansion

Osler, Saskatchewan

completeWastewaterCC
Federal contribution
$414,885
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of OSLER
Construction start
Aug 16, 2010(actual)
Construction end
Sep 25, 2012(actual)

Against the original forecast

  • Construction start16 months lateforecast May 1, 2009
  • Construction end4 months earlyforecast Jan 14, 2013

Also in Osler

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22608 in the federal list. How to read these figures.