Stormwater System Upgrade
Federal contribution
$376,068
Federal share50%
of $752.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
2018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Osler
- Construction start
- Jul 30, 2017(actual)
- Construction end
- Jun 30, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 27, 2017
- Construction end6 months earlyforecast Dec 31, 2018
Also in Osler
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50046 in the federal list. How to read these figures.