Pouce Coupe Lagoon Berm Stabilization

Pouce Coupe, British Columbia

completeWastewaterCC
Federal contribution
$87,083
Federal share33%

of $261.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Pouce Coupe
Construction start
Oct 9, 2010(actual)
Construction end
Dec 31, 2011(actual)

Against the original forecast

  • Construction start19 months lateforecast Mar 5, 2009