Sewage Treatment Plant Works - Sludge Management System
Federal contribution
$66,176
Federal share32%
of $205.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2015
2016201720182019
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Pouce Coupe
- Construction start
- Oct 5, 2015(actual)
- Construction end
- Sep 27, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 31, 2015
- Construction end2.1 years earlyforecast Oct 15, 2021