Sewer Lift Upgrade and Expansion
Federal contribution
$383,333
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Langham
- Construction start
- Nov 23, 2009(actual)
- Construction end
- Nov 26, 2012(actual)
Against the original forecast
- Construction start7 months lateforecast May 1, 2009
- Construction end16 months earlyforecast Mar 31, 2014
Also in Langham
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22709 in the federal list. How to read these figures.