New Wastewater Lagoon - Town of Langham
Federal contribution
$1.9M
$1,948,100
Federal share33%
of $5.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 12, 2016
201720182019202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Town of Langham
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Oct 27, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 1, 2017
- Construction end13 months earlyforecast Nov 30, 2022